Epoxy or Polyurethane? Choosing the Right Crack Injection for the Project

Epoxy bonds dormant structural cracks; polyurethane seals leaking ones. How engineers choose, how injection works, and when it isn't the answer.

Crack injection ports along a concrete crack ready for epoxy or polyurethane injection

Use epoxy when a dormant crack needs its structural strength restored: it bonds the two faces back together. Use polyurethane when a crack is leaking water or may still move: it seals and stays flexible but adds no strength. The engineer decides which applies, based on what caused the crack and whether it's still moving.

Two different tasks: structural cracks vs leaking cracks

Crack injection gets talked about as one service, but epoxy and polyurethane do different things.

Epoxy: structural bonding

Low-viscosity structural epoxy is injected under pressure to fill the crack and bond the concrete back together. Once cured, it is typically stronger than the surrounding concrete. It's the right tool when the engineer wants the element to act as one piece again, for example cracked beams, slabs, columns or walls where the cause has been dealt with and the crack has stopped moving. Epoxy needs a reasonably dry crack to bond well, and it is rigid: if the crack moves again, it will crack again, usually next to the repair.

Polyurethane: sealing water out

Polyurethane resins react with water. Some foam and expand, others cure to a flexible gel or elastomer. They're used to stop active leaks through basement walls, lift pits, retaining walls, slabs and joints. Because they stay flexible, they tolerate some ongoing movement. They don't restore structural strength, so a polyurethane injection on a structural crack is a waterproofing fix, not a structural repair.

Some cracks need both. A structural crack that is also leaking may be stopped with polyurethane first, then bonded with epoxy once it is dry, if the engineer specifies it.

Live or dormant: the question that decides it

A dormant crack has stopped moving. It formed from a one-off cause, such as early shrinkage, a past overload or settlement that has finished. A live crack is still opening and closing, because of thermal cycling, ongoing settlement, vibration or a structural problem that hasn't been fixed.

Rigid epoxy in a live crack is a short-term fix. The movement just finds the next weakest line. So before anything is injected, someone needs to know whether the crack is still moving. Engineers typically find out by:

  • Installing crack monitors (tell-tales) and reading them over a period.
  • Comparing measured widths against earlier records or photos.
  • Assessing the cause: shrinkage, thermal, settlement, corrosion or structural.

If the crack is caused by corroding reinforcement, injection isn't the fix at all. That's a concrete cancer repair, which is covered below.

What the engineer specifies

On structural work, the engineer's specification normally covers:

  • Which cracks to inject, usually from a crack map with widths and lengths.
  • The resin type (structural epoxy or polyurethane) and any performance requirements.
  • Width ranges to treat, and what to do with cracks below or above that range.
  • Surface preparation, port spacing and sealing requirements.
  • Testing or verification, such as cores taken through injected cracks to confirm penetration.
  • Hold points and any related works, such as strengthening or coatings afterwards.

We inject to that specification. We don't design or certify structural work, and we don't substitute materials without the engineer's sign-off.

The injection process

  1. Clean and prepare. The crack line is cleaned so the surface seal and ports bond properly.
  2. Install ports. Injection ports (packers) are fixed along the crack, either surface-mounted or drilled in at an angle to intersect the crack, at spacings that suit the crack width and element thickness.
  3. Seal the surface. For epoxy, the crack face between ports is sealed with a paste so resin stays in the crack under pressure. Polyurethane on a wet, leaking crack is usually injected through drilled ports with less reliance on a surface seal.
  4. Inject. Resin is pumped in at the lowest or first port until it appears at the next, then the injector moves along. On vertical cracks, work runs from bottom to top.
  5. Cure and finish. Once the resin has cured, ports are removed and the surface is ground or made good, ready for coating or finishes.

Crack mapping and records

Good crack injection starts and ends with a map. Before work starts, each crack is identified, numbered and recorded with its location, length and width, with photos. During the project, the record shows the resin used, batch numbers, the ports injected and anything unusual, such as a crack that took far more resin than expected, which can point to a void behind it.

That map becomes your repair register for the injection scope. It's what the engineer uses to release hold points, what you use to measure quantities, and what the next person needs if a crack returns. We hand it back with the project records.

When injection isn't the answer

  • Corrosion cracking. Cracks along the reinforcement from rusting steel need breakout and steel treatment. Injecting them traps the problem. See concrete cancer and spalling repair.
  • Live cracks where the cause continues. Treat the cause first, or the engineer may call for a flexible sealant detail or a movement joint instead. See joint sealing.
  • Capacity shortfall. If the element is cracking because it is under-strength, the engineer may need strengthening. Injection alone won't add capacity. See carbon fibre strengthening.
  • Crazing and fine surface cracking. These are usually better dealt with by a surface treatment or coating than by injection.

Questions builders ask us

Will the crack come back after injection?

If the crack was dormant and the right resin was used, epoxy injection is a permanent bond. If the crack is still moving, a rigid repair can re-crack nearby. That's why the live-or-dormant question comes first.

Can you inject a crack that's actively leaking?

Yes. Water-reactive polyurethane is designed for exactly that. Just be clear it's a seal, not a structural repair.

What drives the price?

The number and total length of cracks, element thickness, access, the resin specified, whether cores or testing are required, and working hours. Send the crack map or engineer's report and we'll price it to that scope.

Can you work around an occupied building or a live site?

Yes. Injection is relatively quiet and contained, so it's staged around your program and the site's permitted hours.

Get a quote on your crack injection scope

Send the engineer's report, crack map or photos to quotes@aussieconcreterepair.com.au or call 0410 515 509. We call back within the hour and send an itemised quote within 7 days. NSW licence 360636C, ACRA member. More on the service: concrete crack injection.

Related guides and services

Aussie Concrete Repair
Aussie Concrete Repair
Team
ACRA member · NSW Licence 360636C · 0410 515 509
Get a quote →or quotes@aussieconcreterepair.com.au
TAKE THE NEXT STEP

Get a quote on your concrete project.

Send photos, the engineer's spec or drawings, or just the symptoms — whatever you've got. The crew reads it and calls you back. No call centre, no obligation.

✓We call back within the hour.
✓You deal with the crew, not a salesperson.
✓Itemised price, built to the engineer's spec.
★ACRA member · NSW Licence 360636C
Get a quote
Tell us about the project. We call back within the hour.
We call back within the hour. No spam, ever.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
📞Get a quote →