Commercial Concrete Repair: How Builders Should Scope the Package

How head contractors should scope a commercial concrete repair package: what to send, how to measure it, hold points, program and the records that close it out.

Commercial concrete repair scope on a carpark slab

Short answer: scope commercial concrete repair from the engineer's specification, price it on measured rates (per litre, per lineal metre, per m²) rather than a lump sum, set the hold points up front, and require a repair register at handover. That keeps variations evidence-based and lets you compare subcontract quotes on the same scope.

1. Start from the specification

Get the engineer's report, repair specification and marked-up drawings before you tender the package. Without them, each subcontractor prices a different assumption and the cheapest quote is usually the one that left the most out.

2. Break the package into measurable items

  • Concrete cancer and spalling repair: per litre of repair volume (see our cost guide).
  • Crack injection: per lineal metre of crack.
  • Joint sealing: per lineal metre of joint.
  • Coatings and floor preparation: per m².
  • Form, reo and pour, strengthening and demolition: per item or element, to the engineer's details.

Measured items make quantity growth after breakout a rate times a measured quantity, not an argument.

3. Set hold points and inspections

Typical hold points: after breakout, after steel treatment, before pour or reinstatement, after CFRP surface preparation, and at completion. Program the engineer visits and group locations so one inspection releases several.

4. Plan access, hours and occupied areas

Access (scaffold, EWP, rope) often costs as much as the repairs on small scopes. Breakout and cutting are noisy and dusty; stage them around trading hours, residents and other trades. Scan before cutting or demolition for reo, post-tensioning and services.

5. Require the records

Ask for a repair register: every location numbered with dimensions, depth, steel condition, before-and-after photos and materials, plus product data sheets and hold-point sign-offs. It's what your superintendent, certifier and client will ask for.

6. One subcontractor or several?

Concrete cancer repair, crack injection, CFRP, joint sealing, coatings, floor levelling and demolition often sit in the same package. One concrete subcontractor across all of them means one program, one register and one point of contact.

Send us the package

Send the specification, drawings and program to quotes@aussieconcreterepair.com.au or call 0410 515 509. We call back within the hour, quote itemised within 7 days, and typically start about 2 weeks after award. NSW licence 360636C, ACRA member.

Related guides and services

Aussie Concrete Repair
Aussie Concrete Repair
Team
ACRA member · NSW Licence 360636C · 0410 515 509
Get a quote →or quotes@aussieconcreterepair.com.au
TAKE THE NEXT STEP

Get a quote on your concrete project.

Send photos, the engineer's spec or drawings, or just the symptoms — whatever you've got. The crew reads it and calls you back. No call centre, no obligation.

✓We call back within the hour.
✓You deal with the crew, not a salesperson.
✓Itemised price, built to the engineer's spec.
★ACRA member · NSW Licence 360636C
Get a quote
Tell us about the project. We call back within the hour.
We call back within the hour. No spam, ever.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
📞Get a quote →