Scan before you cut, saw cutting vs breaking, dust, noise, hours and waste: how to run concrete demolition in occupied Sydney buildings.

Concrete demolition in an occupied building comes down to three things: scan before you cut so you don't hit post-tension tendons, services or critical reo; choose saw cutting over breaking wherever noise, vibration and dust matter; and plan hours, dust control and waste removal around the people still using the building. Do that and the program keeps moving.
Breaking out concrete on an empty site is mostly about production. In an occupied building, with offices above, tenants next door or a carpark still running, the work is about control. Noise travels through the structure, dust finds every gap, and a hit tendon or cut conduit doesn't just stop your project, it can stop the building. Most of the planning happens before anyone picks up a saw.
Every slab, wall and beam we cut is scanned first. Ground-penetrating radar (GPR) and related scanning locate what's inside the concrete so the cut lines can be set around it.
Many commercial slabs in Sydney are post-tensioned. Cutting a stressed tendon is a serious safety hazard, it can damage the structure, and the fix is specialist and slow. If the drawings say PT, or nobody is sure, the slab is treated as PT until scanning and the engineer say otherwise. Any penetration through a PT slab needs the engineer's approval of its location.
Conduits, cables and pipes are often cast into slabs and walls, and as-built drawings aren't always right. Scanning marks them before the cut, so the electrician isn't chasing a dead circuit at 2am.
Scanning also shows reo layout and approximate cover. That lets the engineer confirm what can be cut, and lets us place cores and cut lines to avoid main bars where the design calls for it.
Scanning reduces risk; it doesn't remove it. Results are marked on the surface and recorded, and anything uncertain goes back to the engineer before cutting.
Most occupied-building demolition is a mix of both, and the ratio drives noise, dust and program.
Slab saws, wall saws and core drills give clean, accurate edges with far less vibration than breaking. Concrete can be cut into sections and lifted or trolleyed out, which suits small openings, stair and lift penetrations, and anywhere the edge needs to stay sound for new work. Wet cutting controls dust, but the slurry has to be captured and cleaned up.
Jackhammers, breakers on small demolition machines and hydraulic splitters remove bulk concrete fast. They're noisy and transmit vibration through the frame. On an occupied building, breaking is usually restricted to agreed hours, and cut-then-break, where the perimeter is saw cut first, keeps the damage zone tight.
Cutting and breaking concrete produces respirable crystalline silica, a serious health hazard regulated by SafeWork NSW. Controls typically include water suppression or on-tool extraction, sealed dust screening, negative air where needed, and the right respiratory protection for the crew.
Noise and vibration are managed through hours and method. Building management, the development consent or tenant leases often set the limits. Agree quiet and noisy windows early, and schedule the loud work for the hours the building allows.
Concrete waste is heavy and access in occupied buildings is tight. The plan needs to cover how it gets out (lifts, hoists, chutes, trolleys or crane), floor protection along the route, bin or truck locations and timing, and separating steel for recycling. Getting the removal path wrong can cost more program time than the cutting itself.
Demolition is rarely the end of the scope. It sets up what comes next:
Having one crew scan, cut, break out and rebuild means fewer handovers between trades and less time lost waiting for the next subcontractor.
Demolition pricing is driven by the volume and thickness of concrete, whether it's PT, cut lengths and core numbers, access and how waste gets out, dust and noise controls, and working-hour restrictions. Send the drawings or a marked-up plan showing what's coming out, the engineer's details or approvals for any penetrations, photos of the area and access route, and any building rules on hours. The more we know about access, the tighter the price.
Only where the engineer has approved the location and it's been scanned and marked clear of tendons. We don't decide where a PT slab can be cut; the engineer does.
No scan is perfect, which is why results are recorded, uncertain readings go back to the engineer, and cut lines are kept clear of marked items. It greatly reduces the risk compared with cutting blind.
Usually, yes. We stage the work, isolate dust, and agree noisy-work hours with building management.
Yes. We form, reo and pour to the engineer's details, or patch where breakout was for repair. Records and a repair register come back to you at the end.
Aussie Concrete Repair is an ACRA member with NSW licence 360636C. Concrete is scanned before cutting, you get a 1-hour callback, and itemised quotes come back within 7 days. Email quotes@aussieconcreterepair.com.au or call 0410 515 509. More on the service: concrete demolition.
Send photos, the engineer's spec or drawings, or just the symptoms — whatever you've got. The crew reads it and calls you back. No call centre, no obligation.