Pacific Hwy | Killara
Project case study

Pacific Hwy | Killara

Slab-on-ground carrying three occupied levels, broken out and reinstated in alternating A-B zones to the engineer's sequence. Every hold point signed off, no residents relocated.

Mini excavator breaking out the failed slab inside the unit, Pacific Hwy, Killara
$250K
Project value
16 weeks
DURATION
Owners Corp
Client

A slab-on-ground at Pacific Hwy, Killara had been carrying three occupied levels for decades. It was cracking and moving, and the structural engineer's report called for the compromised sections to be broken out and reinstated. The catch: the slab was the load path for the building, and nobody above could be moved out.

The problem

This wasn't a cosmetic crack repair. Every square metre of slab that came out was carrying load from the floors above. Open too much at once and the structure moves. Get the sequence wrong and residents notice it in their walls and doors before anyone on site does.

The brief

  • Keep the load path continuous at every stage. No zone left unsupported.
  • Work to the engineer's staging sequence, with a hold point before each zone opened.
  • Keep the building occupied and running for the whole program.

How we delivered it

  • A-B staging. The slab was split into alternating zones so support stayed continuous across the floor at all times. Zone B only opened once Zone A was poured, cured and signed off.
  • Breakout. Compromised sections cut and removed zone by zone, the same sequence we use for slab removal in occupied buildings.
  • Reinforcement. New bar fixed and dowelled into the existing slab to the engineer's details. See our reo replacement and dowelling work.
  • Form, reo and pour. Each zone formed, poured and cured before the next opened. This is our form, reo and pour service at full scale, and the same method behind large breakout reinstatement.
  • Hold points. The engineer inspected and signed off each zone before work moved on.
  • Occupied-building controls. Dust, noise and access managed around residents every day.

The result

  • Slab reinstated to the engineer's specification, with sign-off at every hold point.
  • Building occupied throughout. No residents relocated.
  • $250K package delivered in 16 weeks.

Why it matters to you

Builders and remedial contractors: if you've got a structural slab in an occupied building, this is the sequence we run, and we'll fit it to your program. Engineers: your staging is followed exactly, with a hold point at every zone. Strata and asset managers: the building stays open while the work happens.

Need a slab broken out and reinstated? Start with our concrete demolition and form, reo and pour pages, or send us the engineer's report.

Ben Tran
General Manager, Aussie Concrete Repair
Class 2 DBP registered · Licence 360636C · 0410 515 509
Talk to Ben →or quotes@aussieconcreterepair.com.au
Similar problem on your building?

Tell us what the building's doing.

Send photos, the engineer's report, or just the symptoms — whatever you've got. A registered builder reads it and calls you back. No call centre, no obligation.

✓5-minute callback in business hours — within 24 hours otherwise.
✓You deal with the builder, not a salesperson.
✓Fixed-price scope, documented and engineer-checkable.
★Class 2 DBP registered · Licence 360636C
Get an assessment.
We usually respond within 1 business day — often within 5 minutes in business hours.
Get a callback →
No obligation · A registered builder calls you, not a call centre
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.