Slab-on-ground carrying three occupied levels, broken out and reinstated in alternating A-B zones to the engineer's sequence. Every hold point signed off, no residents relocated.

A slab-on-ground at Pacific Hwy, Killara had been carrying three occupied levels for decades. It was cracking and moving, and the structural engineer's report called for the compromised sections to be broken out and reinstated. The catch: the slab was the load path for the building, and nobody above could be moved out.
This wasn't a cosmetic crack repair. Every square metre of slab that came out was carrying load from the floors above. Open too much at once and the structure moves. Get the sequence wrong and residents notice it in their walls and doors before anyone on site does.
Builders and remedial contractors: if you've got a structural slab in an occupied building, this is the sequence we run, and we'll fit it to your program. Engineers: your staging is followed exactly, with a hold point at every zone. Strata and asset managers: the building stays open while the work happens.
Need a slab broken out and reinstated? Start with our concrete demolition and form, reo and pour pages, or send us the engineer's report.
Send photos, the engineer's report, or just the symptoms — whatever you've got. A registered builder reads it and calls you back. No call centre, no obligation.